Information Notice to Owner at time of contract execution for residential projects.

“Levelset takes something that is pretty complex and makes it easy.”
Not sure? Calculate your deadline for free.
Information Notice to Owner at time of contract execution for residential projects.

Lien must be filed w/in 75 days after last labor or materials furnished, or completion of project; whichever is earlier.
Generally, an action to enforce an Oregon mechanics lien must be initiated within 120 days after the filing of lien.
Oregon has a unique enforcement deadline, however, in that this time may be extended in periods of 120 days for up to 2 years. In order to extend the deadline, an extended payment plan must be arranged between the parties with the terms of the plan stated in the lien itself.
Notice of right to lien served on owner (and lender, if any) within 8 days of providing labor/materials on residential projects.
For some, it will be required on commercial projects. See Preliminary Notice FAQ page for more information.

Lien must be filed w/in 75 days after last labor or materials furnished, or completion of project; whichever is earlier.
Generally, an action to enforce an Oregon mechanics lien must be initiated within 120 days after the filing of lien.
Oregon has a unique enforcement deadline, however, in that this time may be extended in periods of 120 days for up to 2 years. In order to extend the deadline, an extended payment plan must be arranged between the parties with the terms of the plan stated in the lien itself.
Notice of right to lien served on owner (and lender, if any) within 8 days of providing labor/materials on residential projects.
See Preliminary Notice FAQ page for more information.

Lien must be filed w/in 75 days after last labor or materials furnished, or completion of project; whichever is earlier.
Generally, an action to enforce an Oregon mechanics lien must be initiated within 120 days after the filing of lien.
Oregon has a unique enforcement deadline, however, in that this time may be extended in periods of 120 days for up to 2 years. In order to extend the deadline, an extended payment plan must be arranged between the parties with the terms of the plan stated in the lien itself.
In Oregon, the parties entitled to mechanics lien rights are clearly defined by statute. This includes general contractors, subcontractors (of any tier), laborers, material suppliers, equipment lessors, and design professionals; such as architects, landscape architects, land surveyors, and registered engineers.
Generally, no. However, a written contract between the original contractor and the property owner is required on projects that are residential or zero-lot-line dwellings if the contract price exceeds $2,000. If, on such projects, there is no written contract, the original contractor may not file a lien arising from the improvement of the property.
If the contract price exceeds $2K during the course of the project, the contractor must deliver a written contract within 5 days of the date the contractor knew, or should have known, that the price exceeded $2K.
• Dive deeper: Can a Contractor File a Lien Without a Written Contract?
Note: if no written contract exists when required, it will not render the contract void, but will preclude the prime contractor from filing a mechanics lien.
No. Oregon requires a lien claimant to be licensed in order to enforce a mechanics lien. Oregon also has specific licensing requirements for contractors, subcontractors, and developers in order to bid on both residential and commercial projects.
Lastly, if a subcontractor is hired by an unlicensed contractor on an owner-occupied, residential project, they will not have lien rights either.
• Learn more: Oregon Contractor Licensing: Applications, Rules, & Requirements
In Oregon, a mechanics lien must be filed either 75 days after the claimant’s last furnishing of labor and/or materials, or 75 days after completion of construction; whichever is earlier.
If the lien is filed prior to the completion of the project or before the last furnishing of labor and/or materials (whichever is appropriate) the lien is premature and invalid.
Note: If a written, formal change order is issued – that may reset the last furnishing date for Oregon mechanics liens.
• More on that here: Change Order Format Can Make or Break Oregon Mechanics Lien Claims.
The form and content of an Oregon mechanics lien can be found under ORS §87.035, and should include the following information:
• Claimant’s name, address, and license number (if required);
• Statement of demand after deducting all just credits and offsets;
• Owner’s name & address;
• Hiring party’s name & address;
• Property description;
• Description of labor and materials provided (preferably with labor and materials separated); &
• Any contractual or statutory interest claimed (if any).
→ Download a free Oregon Claim of Construction Lien form here
No. Oregon requires that the mechanics lien statement only include a description of the property sufficient for identification, including the property address if known. However, the more identifying information the better.
Generally, an Oregon lien amount is limited to the contract price. However, claimants may include any contractual interest (if any), and the recording fee of the lien claim. Outside of that, no other amounts may be included.
If successful in foreclosure proceedings, However, reasonable attorney fees and court costs may be awarded as well.
• Dive deeper: Mechanics lien amounts | What can you include in each state?
Yes. Oregon law requires that a mechanics lien must be notarized to be valid and accepted for recording.
• Learn more about notarizing construction payment documents
• Options for notarizing mechanics liens remotely
Oregon mechanics lien claims are documents recorded with the county recorder’s office. For your mechanics lien to be valid, you must record it in the county where the job is physically located.
Oregon counties each have their own unique rules and requirements. To help you, we’ve assembled all of the offices in Oregon that record mechanic’s lien claims. These pages will walk you through the county’s specific formatting requirements, deadlines, and fees.
• Be prepared: Essential Questions to Ask The County Recorder Before Filing a Lien
There are a lot of questions answered on this page about who can file an Oregon mechanics lien, when it must be filed, what types of rules apply, and more. But you may be wondering something much more practical: how do I actually get my mechanics lien recorded and filed in Oregon?
• For this, you may want to consult our Step-by-Step Guide on How to File an Oregon Mechanics Lien.
Best practice is to send notice that the lien was filed (a copy of the lien) to the owner, mortgagee, and anyone with a previously recorded security interest in the property within 20 days from the filing of the lien. A copy of the lien claim must be included and served by personal service, certified mail return receipt requested, or other methods with written third-party verification of delivery.
Note: Failure to send notice isn’t fatal to the lien claim, but will result in the forfeiture of the right to attorney fees and costs in a foreclosure action.
An action to enforce an Oregon mechanics lien must be initiated within 120 days after the filing of the lien.
• Find an Oregon construction attorney
However, this time may be extended in periods of 120 days for up to 2 years; but only if an extended payment plan has been arranged between the parties and the terms of the plan are stated in the lien itself.
Note: A Notice of Intent to Foreclose must be sent to the owner and any mortgagee at least 10 days prior to filing the foreclosure action.